year |
Major events |
1986-1988 |
Preliminary explored 7 possible dam sites to assess conditions such as topographical geology, water supply capacity, and inundation area at each dam site. |
1989-1991 |
The Institute conducted an assessment of the possible dam sites of No. 2-1 and No. 2-2. The results of the analysis on geology and economy showed that the possible dam site No. 2-2 was more feasible. |
1991 |
The Institute conducted preliminary survey and planning tests for the Second Baoshan Reservoir, including: surface geological survey, geological drilling test, dam material survey and test, topographic survey, and hydrology and water source analysis. |
1993-1994 |
- Convene a reservoir planning project description meeting - explain the current planning progress and discuss the borrowing area planning and related matters.
- Handle preliminary and feasibility planning work. For meteorological and hydrological review and analysis, reservoir inundation area survey and engineering planning design review and assessment, hydropower research, engineering materials survey and test, surface geological supplement survey, engineering geological survey and assessment, review of resettlement plan, environmental impact survey assessment, the Second Baoshan Reservoir operation and maintenance Guidelines, engineering materials investigation and testing establish a preliminary geographic information system, basic design drawings and geological surveys, and demolition and resettlement plans
|
1993 |
In response to the newly enacted environmental impact assessment law (December 30, 1994), the environmental impact statement of Second Baoshan Reservoir was prepared in 1993. |
1996 |
The Institute conducted related planning for the joint use of Second Baoshan Reservoir with other Weir.
Environmental Protection Administration announced “the environmental impact statement of Second Baoshan Reservoir in Hsinchu County is conditional development" on September 7, 1996. |
1997-2006 |
The Second Baoshan Reservoir began construction in April 1997 and completed in June 2006. The total project cost is 10.5 billion TWD. The main purpose is to improve the water storage capacity of Hsinchu, and it can be combined with Baoshan Reservoir to increase the water supply by 282,000 CMD, which can improve the water supply and water supply stability in Hsinchu. |